The Europipe II pipeline is 658 kilometres long and has an internal diameter of 42 inches.

It transports gas from the Kårstø processing complex north of Stavanger to the receiving facilities at Dornum in northern Germany.


This system became operational in 1999.


From

Kårstø

To

Dornum, Germany

Length

658 km

Diameter

42 inches

Available technical capacity (ATC)*

71 Mscm/d

Technical service provider (TSP)

Statoil

Operator

Gassco

Gassled

Area D

 

 