Europipe II
The Europipe II pipeline is 658 kilometres long and has an internal diameter of 42 inches.
It transports gas from the Kårstø processing complex north of Stavanger to the receiving facilities at Dornum in northern Germany.
This system became operational in 1999.
| From |
Kårstø |
| To |
Dornum, Germany |
| Length |
658 km |
| Diameter |
42 inches |
| Available technical capacity (ATC)* |
71 Mscm/d |
| Technical service provider (TSP) |
Statoil |
| Operator |
Gassco |
| Gassled |
Area D |
* ATC (Available Technical Capacity) is rounded to the nearest whole number [MSm³/d]. The actual transport capacity, available for potential users of these pipelines, could be influenced by pressure dependencies between different pipelines, temperature, gas quality, operational constraints etc.
